| |
Bahrain International Airport Extensions To Terminal Building
And Associated Works
Phase 1 and 2 of the works were mainly confined to the landside
of Bahrain International Airport comprising the following
designed by Scott Wilson Kirkpatrick.
* A new extension to the existing
terminal together with refurbishment of the existing terminal
building. The new extension is just over twenty thousand
square metres in area. Refurbishment work involved internal
alterations and modification of finishes and services to
maintain compatibility with the new extension to the building.The
buildings have a structural steel frame with concrete floors
and aluminium/glass curtain walling
* Extension and refurbishment
of the existing services building and installation of new
air conditioning plant. Upgrading of the air conditioning
and other building services in the existing terminal also
formed part of the works.
* Extension of the existing
ground level car-park and a new elevated road to serve the
new high-level departure concourse.
* The supply and installation
by Nominated sub-contractors of specialist equipment including
Passenger Loading Bridges, Flight Information Display Systems,
Baggage Handling Equipment, Lifts & Escalators.
Scott Wilson Kirkpatrick were also engaged for Phase 3 to
design the reinstatement of work deferred at the tender
negotiation stage.
The reinstated work largely involved finishes, certain mechanical
and electrical services, elements of flight information
display handling system and other specialist facilities.
The most significant effect of the Phase 3 works was to
increase the usable areas of the Level 'O' public arrivals
concourse and level '6' landslide departure concourse by
40% and 50% respectively, over those made available for
use at the opening of Phase 1. In particular it resulted
in an increase number of check-in desks from 24 to 40.
When work commenced in the existing terminal building it
became apparent that all the structural concrete (poured
in 1971) was defective. It was necessary, therefore, to
demolish and replace all structural elements within the
existing building.
The total cost of Phase 1, 2, 3 and slab replacement amounted
to approximately BD 35 million. Scott Wilson Kirkpatrick
appointed D.G. Jones & Partners to integrate within their
team to provide full pre and post contract quantity surveying
services. D.G. Jones & Partners pre-contract services commenced
in 1985 and the project was finally completed on site in
August 1997.
|